Gwayi-Shangani Dam is 82% complete, but Bulawayo pipeline stands at 15%

Matabeleland Pulse Reporter
Gwayi-Shangani Dam is 82% complete, but Bulawayo pipeline stands at 15%
The Gwayi-Shangani Dam is 82% complete, but the pipeline intended to transport water towards Bulawayo is only 15% complete, according to project progress figures presented in the 2027 National Budget.
The figures highlight the different stages of progress across the infrastructure components of the major water project, which is expected to play an important role in addressing Bulawayo’s long-term water supply challenges.
In its project update under the heading “Dam Projects”, the Ministry of Finance lists the Gwayi-Shangani Dam at 82% completion.
However, the accompanying infrastructure is considerably further behind.
The budget presentation lists the “Gwayi Shangani Bulawayo Pipeline” at 15% completion, while the “Gwayi Shangani – Bulawayo Pipeline Booster Pump Stations” are at 18%.
The difference is significant because completing the dam alone would not mean that water can immediately be transported to Bulawayo. The pipeline and associated pumping infrastructure are essential parts of the wider water supply system.
The presentation does not provide a completion date for the pipeline or explain the reasons behind the difference in progress between the dam and the associated infrastructure.
Other water projects in Matabeleland are also at varying stages of completion.
Vungu Dam in Matabeleland North is listed at 46%, while Ziminya Dam stands at 32%. In Matabeleland South, Tuli-Manyange Dam is reported to be 34% complete.
Meanwhile, the Cowdray Park Water Treatment Plant in Bulawayo is listed at just 2% completion.
The figures raise important questions about the remaining work, funding requirements and implementation timelines for water infrastructure projects in the region.
For Bulawayo residents, the critical issue is not simply how close the dam is to completion, but when the entire system required to deliver water will be ready.
The budget presentation provides progress percentages but does not give a detailed breakdown of outstanding work, expenditure to date, or expected commissioning dates.